-80%

MMPO-002 Project Management Solved Question Paper June 2024

Current price is: ₹20.00. Original price was: ₹100.00.

MMPO-002 Project Management
Solved Question Paper June 2024
Project Management
Course Code: MMPO-002

Current price is: ₹20.00. Original price was: ₹100.00.

Add to cart
Buy Now
SKU: MMPO-002 JUNE 2024 DOWNLOAD Categories:

MMPO-002 Project Management Solved Question Paper June 2024

Project Management
Course Code: MMPO-002

Title NameMMPO-002 Solved Question Paper June 2024
UniversityIGNOU
Service TypeSolved Question Paper (Soft copy/PDF)
CourseMBA / Management
Language English
YearJune 2024
Course CodeMMPO-002
ProductSolved Question Paper  (IGNOU)

1. What is a project ? What are the five process
groups and ten knowledge area as prescribed by
PMBOK guide 6th edition ? Discuss the ten
knowledge area.
2. What do you mean by a project charter ? What
are the contents of project charter ? Discuss a
sample project charter with which you are
familiar.
[ 2 ] MMPO–002
3. What is forward pass and backward pass ?
Explain the determination of the earliest and
the latest start and completion times of the
different activities of a project. Also, explain
how the earliest and the latest event times are
obtained.
4. What is Earned Value Analysis (EVA) ?
Discuss the performance metrics of Earned
Value.
5. What do you mean by ‘Agility in Project
Management ? What are the guiding principles
of an agile project ? Discuss.
6. What is project audit ? What are the various
types of project Audits ? How to audit a
project ? Discuss.
7. Write a short note on any four of the following :
(i) Dimensions of project feasibility
[ 3 ]
(ii) Work Breakdown Structure (WBS) of a
motorcycle
(iii) Integrated Project Management
Information System
(iv) Project Risk Breakdown Structure
(v) Public Private Partnership